Commissioning runs and technical missions on ESPRESSO.
| Commissioning run | Start date | End date | Tested modes and telescopes |
|---|---|---|---|
| First light | 27/11/2017 | ||
| Commissioning 1A | 27/11/2017 | 06/12/2017 | HR and UHR modes, all UTs |
| Commissioning 1B | 26/01/2018 | 07/02/2018 | All modes and all configurations |
| Commissioning 2A | 25/02/2018 | 07/03/2018 | All modes, all UTs |
| Technical activities | 07/03/2018 | 21/03/2018 | All subsystems |
| Commissioning 2B | 27/04/2018 | 05/05/2018 | HR and UHR mode, all UTs |
| Technical activities | 13/09/2018 | 21/09/2018 | Vacuum and cryogenics optimization |
| Official start of operations | 01/10/2018 | ||
| Technical activities | 03/10/2018 | 23/03/2018 | Optical efficiency tests and re-alignment |
| Commissioning 2C – July 2018 | 03/07/2018 | 09/07/2018 | All modes and all configurations |
| 4-UT Commissioning – December 2018 | 30/11/2018 | 01/12/2018 | MR mode, all UTs |
| Technical activities | 08/06/2019 | 27/06/2019 | Fiber upgrade |
| Recommissioning – July 2019 | 27/06/2019 | 08/07/2019 | All modes and all configurations |
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.